Introduction to Microsoft Project Desktop Series Ep. 1: Tasks
Welcome to a comprehensive guide on Microsoft Project Desktop, led by Yasmine Brooks, aimed at project managers looking to master the fundamentals of Microsoft Project through a series of engaging, hands-on tutorials. This post summarizes the essential steps and techniques introduced by Brooks in the initial video of the series, providing a clear roadmap for anyone starting with Microsoft Project.
Getting Started with Project Desktop
Yasmine kicks off the series by emphasizing the hands-on nature of the tutorials, encouraging viewers to follow along with Project Desktop. The initial focus is on creating a project from scratch, setting a foundation for future videos where this starting file will be built upon. Key to this process is the emphasis on saving work, as these files become the basis for subsequent lessons.
Step-by-Step Project Creation
Brooks outlines the critical steps for starting a project in Microsoft Project Desktop:
- Task Listing:
- Begin by listing all project tasks in the Task Name column.
- This step involves simply entering the names of tasks, such as Task 1, Task 2, etc.
- Duration Estimation:
- Next, estimate the duration of each task in the Duration column.
- Durations are critical for scheduling and planning, with each task assigned a specific number of days for completion.
- Task Scheduling:
- Initially, tasks are scheduled to occur simultaneously, which is often not practical.
- Brooks demonstrates how to create task relationships, linking tasks in a logical sequence using the "Link Tasks" feature. This step organizes tasks into a coherent schedule, reflecting the real flow of work.
- Adjusting Task Durations:
- Project plans are dynamic; task durations can change based on new information or requirements.
- Brooks shows how to update task durations and discusses the importance of auto-scheduling for dynamic project management.
- Auto vs. Manual Scheduling:
- By default, tasks are set to "Manually Scheduled," which can lead to issues in task alignment and scheduling.
- Switching to "Auto Schedule" mode is recommended for a more efficient scheduling process, ensuring tasks are automatically adjusted in response to changes.
- Configuring Project Settings:
- Brooks guides viewers through adjusting project settings to default to "Auto Schedule" for new tasks, streamlining project setup for future tasks and projects.
Planning a Real Project: Painting a Room
Transitioning from theory to practice, Brooks applies the discussed principles to plan a real project—painting a living room. This section covers:
- Project Breakdown: The project is broken down into phases (Planning, Prepping, Execution, Cleaning), with each phase consisting of specific tasks. This structured approach simplifies project management, allowing for easier tracking and adjustment of tasks and phases.
- Phases and Summary Tasks: Brooks demonstrates how to organize tasks into phases, using the "Indent" feature to create a hierarchy within the project. Summary tasks aggregate durations and provide an overview of each phase, enhancing project visibility.
- Duration Estimation for Phases: For each phase, tasks are given estimated durations, factoring in the specifics of the painting project, such as choosing paint colors and preparing the room. The importance of accurate estimation and the impact of task durations on the project timeline are highlighted.
Key Takeaways and Next Steps
The introductory videos of the Microsoft Project Desktop series, as summarized above, equip project managers with the knowledge to start, plan, and organize their projects effectively. Brooks emphasizes the importance of hands-on practice, incremental learning, and adaptation to project changes.
Future videos promise to delve deeper into task relationships, project tracking, and advanced scheduling techniques. This serves as a primer, encouraging viewers to explore the series further for comprehensive project management skills development in Microsoft Project Desktop.
Don't forget to check out the Pragmatic Works' on-demand learning platform for more insightful content and training sessions on Microsoft Project and other Microsoft applications. Like and subscribe to the Pragmatic Works YouTube channel to stay up-to-date on the latest tips and tricks.
Sign-up now and get instant access
ABOUT THE AUTHOR
Yasmine Brooks is a former BI consultant with 6 years of experience in Healthcare as a Radiation Oncologist and Operations Manager in her home country of Brazil. She is the proud mother of a sweet baby girl, a dog lover, and soccer fan. She is always seeking new foods and travel destinations.
Free Trial
On-demand learning
Most Recent
private training
Leave a comment